Re: Old basic dates should be loaded in the new system for Maintenance Orders

$
0
0

I assume you are just talking about cut over orders. In future you want the auto scheduling to work as is .

 

So in that case you may turn off scheduling convert all Orders , Release the Orders , and as a last step update the Basic start and Finish date .Once you are done with Cutover activities  you may enable automatic scheduling in configuration again.

 

Anjan